Product guide20 min read

Importing solar panels into India in 2026: BIS registration, ALMM lists, REEIMS and e-waste rules

Solar PV modules need a BIS registration held by the factory under MNRE's 2025 solar order, with at least 17-18% efficiency, plus REEIMS registration for project shipments and e-waste EPR. ALMM listing matters only for government, scheme, net-metering and open-access projects.

In effect from
27 July 2025
ALMM List-II (cells)
Effective 1 June 2026
ALMM List-III (wafers)
Effective 1 June 2028
On this page
  1. Key facts
  2. What do you need to import solar panels into India?
  3. Which approvals do solar panels need? The full table
  4. What HS code is used for solar panels?
  5. Which solar panel variants are borderline, and what does each need?
  6. Are solar panels free to import, or restricted?
  7. How do you get approval for solar panels, step by step?
  8. How does BIS registration work for solar panels?
  9. When did BIS registration become compulsory for solar panels?
  10. What is ALMM and does it apply to imported solar panels?
  11. Can imported modules be used in rooftop and government projects after June 2026?
  12. What is REEIMS registration for solar imports?
  13. Do solar panels need e-waste EPR registration?
  14. Do solar panels need battery EPR, plastic EPR or LMPC registration?
  15. What must be marked on an imported solar panel?
  16. What should you check on a solar module label before it ships?
  17. How much does BIS and EPR approval cost for solar panels? A worked example
  18. What does the solar panel cost example leave out?
  19. What does it cost to certify three solar module families?
  20. How long does it take to get solar modules approved and cleared?
  21. Three common solar panel import situations
  22. Who is responsible for what: factory, importer, EPC or seller?
  23. Where do solar panel shipments get stuck?
  24. What happens if you import solar panels without these approvals?
  25. What changes for solar panels in 2026 and 2027?
  26. Where can you get help with solar module approvals?
  27. Frequently asked questions
  28. Sources

Key facts at a glance

Governing order
Solar Systems, Devices and Components Goods Order, 2025 (MNRE)[1]
In effect from
27 July 2025[2]
Indian Standards
IS 14286 (Part 1/Sec 1):2023 + IS/IEC 61730-1 & -2[3]
Minimum efficiency for BIS
18% mono / thin film; 17% poly[3]
HS code
85414300 (modules); 85414200 (cells)[4]
REEIMS registration
From 1 Nov 2025, free, valid 3 months[4]
ALMM List-II (cells)
Effective 1 June 2026[5]
ALMM List-III (wafers)
Effective 1 June 2028[6]
E-waste code
CEEW14, no recycling target[7]
BEE label
Voluntary, Rs 0.025 per watt[8]
BIS licence validity
5 years, renewable for 5[9]

Checked 1 November 2026 against the regulator's own documents.

What do you need to import solar panels into India?

Solar panels (PV modules) are regulated by the Ministry of New and Renewable Energy (MNRE), not MeitY, but the certificate still comes from BIS. For a standard crystalline or thin-film module you need:

  1. BIS CRS registration, held by the factory, under MNRE's Solar Systems, Devices and Components Goods Order, 2025[1]. The order has been in effect since 27 July 2025[2].
  2. A module that meets the efficiency floor: 18% for mono-crystalline and thin-film, 17% for poly-crystalline, or BIS will not grant the licence[3].
  3. REEIMS registration on MNRE's import monitoring portal before each shipment of modules meant for solar energy projects, from 1 November 2025[4].
  4. E-waste EPR registration with CPCB, because solar modules are a Schedule I item (CEEW14)[7]. There is no recycling target; you store and report instead[7].
  5. Plastic packaging EPR if the pallets or modules come wrapped in plastic.

Then there is the rule that decides who can buy your panels. ALMM, MNRE's Approved List of Models and Manufacturers, applies to government, government-assisted, scheme, net-metering and open-access projects[10]. It is not an import licence. But if a module is not on ALMM List-I, most rooftop and utility buyers cannot use it.

Not required: a WPC ETA or TEC MTCTE (a module has no radio or telecom function). The BEE label is voluntary for PV modules[8].

Check your own product mix with the approval checker, or ask us for a free compliance check.

Which approvals do solar panels need? The full table

Fees are the official published amounts, excluding GST. "Time" is the official service standard where one exists.

Approvals for importing solar PV modules into India (2026)
ApprovalWhy it appliesWho holds it / issues itOfficial feeTimeValidity
BIS CRS (Scheme-II)Modules are notified under MNRE's 2025 order[1]Factory holds it; BIS issuesRs 1,000 application + Rs 50,000 processing (one test report) + Rs 1,000 a year[11]20 working days if documents are clean[12]5 years, renewable for 5[9]
ALMM List-I enlistmentNeeded only for government, scheme, net-metering and open-access projects[10]Manufacturing unit; MNRE enlistsNot covered in our researchNot publishedOnly while BIS registration is valid[13]
REEIMS import registrationModules (85414300) for solar energy projects[4]Importer (IEC holder); MNRE portalNo fee[4]File 2 days before air, 5 days before sea/land arrival3 months, one port
E-waste EPR registrationSolar PV modules are EEE code CEEW14[7]Importer as producer; CPCBRs 10,000 for a producer whose sales have just started, per CPCB SOP[14]-Annual returns to 2034-35[7]
Plastic packaging EPRIf the import includes plastic packaging[15]Importer; CPCBRs 10,000 under 1,000 TPA[16]-Annual returns
LMPC importer registrationOnly for retail pre-packs; industrial and institutional packs are exempt[17]Importer; State Legal MetrologyRs 500[18]Apply within 90 days of first import[18]Until cancelled[19]
BEE labelVoluntary for PV modules[8]Brand; BEERs 0.025 per watt label fee[8]--

What HS code is used for solar panels?

85414300 is the ITC(HS) line for "Photovoltaic cells assembled in modules or made up into panels". Bare cells, not yet laminated into modules, are 85414200[4]. Both are "Free" imports, but since 1 November 2025 they carry Policy Condition 09 of Chapter 85, the REEIMS registration rule[4].

The same DGFT notification also brings toughened solar glass (70071900) under REEIMS when it is used exclusively for solar energy projects[4].

Borderline cases to settle with your customs broker:

  • Solar kits sold with a charge controller, battery or inverter in one box. The module, solar inverter and battery each have their own BIS category, so each needs its own registration.
  • Portable folding panels with a built-in USB output. They are still PV modules for BIS. If a battery is built in, battery EPR applies too.
  • Cells only. Cells are not a BIS CRS item in the 2025 order. They matter for ALMM List-II, which applies to the modules made from them[5].

Which solar panel variants are borderline, and what does each need?

The module technology decides the Indian Standard, the buyer decides ALMM, and anything built in (battery, USB port) adds its own rules. This matrix covers the variants importers ask about most. Rows marked "our reading" are not covered by an official ruling.

Solar module variants and their approvals
VariantBIS standard setREEIMSALMMOther
Crystalline silicon module (mono or poly)IS 14286 (Part 1/Sec 1):2023 and IS/IEC 61730-1 and -2[3]Yes, if for a solar energy project[4]Only for govt, scheme, net-metering, open access[10]Efficiency floor 18% mono, 17% poly[3]
Thin-film module (CdTe, a-Si, CIGS)IS 14286 (Part 1) thin-film sections[3]SameSameEfficiency floor 18%[3]
Bifacial or high-wattage variant of a listed seriesSame series, retest under IS/IEC TS 62915 if the bill of materials changes[20]SameSeparate ALMM model if not enlistedEach wattage family may need its own report
Bare PV cellsNot a BIS item in the 2025 orderYes, 85414200[4]List-II, for modules made from them[5]-
Solar glassNot a BIS item hereYes, 70071900[4]No-
Portable folding panel with USB outputStill a PV module for BIS (our reading)Only if for a projectNoLMPC retail declarations[18]
Folding panel with built-in batteryPV module plus the battery question; ask your labNoNoBattery EPR[21]; see lithium-ion battery packs
Module with an attached microinverter (AC module)Module standards plus the PV inverter item (our reading)[3]Yes for the moduleYes if in scopeBEE label for grid-connected inverter part[22]

Are solar panels free to import, or restricted?

Solar modules and cells are 'Free' imports, but since 1 November 2025 they carry Policy Condition 09 of Chapter 85, the REEIMS registration rule[4]. No DGFT licence is needed. Three things work like gates in practice:

  1. BIS. Covered goods cannot be imported, sold or stored for sale without conforming and carrying the Standard Mark[23].
  2. REEIMS. Shipments for solar energy projects must be registered before arrival[4].
  3. ALMM. Not a customs condition, but it decides whether government, scheme, net-metering and open-access buyers can use your modules[10].

Customs also checks EPR: CPCB asked CBIC in June 2025 to verify plastic EPR registration when clearing imports[24]. Keep all registrations with your customs clearance documents, and use the HS code approval finder to cross-check a line before you file the bill of entry on ICEGATE.

How do you get approval for solar panels, step by step?

In this order. The factory side (BIS, ALMM) takes longest; start it first.

  1. 1
    Check the efficiency of every model

    Calculate efficiency at STC as Pmax / (1000 x area) x 100. Models below 18% (mono, thin film) or 17% (poly) cannot get a licence[3]. If you sell to ALMM projects, check the higher ALMM thresholds too[13].

  2. 2
    Factory registers on the CRS portal

    The manufacturer gets a crsbis.in login using its business licence in English[25]. A foreign factory nominates an Authorised Indian Representative[12].

  3. 3
    Group the models and test them

    Form the series under clause 4 of IS 14286 (Part 1), with retests for any bill-of-materials change under IS/IEC TS 62915[20]. Send samples to a BIS-recognised lab within 60 days of the test request[25].

  4. 4
    Apply for CRS

    Apply within 90 days of the test report's issue[12]. The lab must report Pmax, module area and calculated efficiency, because BIS checks them against the order[20].

  5. 5
    Apply for ALMM if your buyers need it

    MNRE enlists the manufacturing unit and model on List-I. Enlistment depends on a valid BIS registration[13]. For projects commissioned from 1 June 2026, the modules must also use List-II cells[5].

  6. 6
    Register with CPCB

    Register on the e-waste EPR portal as a producer of solar PV modules[7], and on the plastic EPR portal if you import plastic packaging[15].

  7. 7
    Register each shipment on REEIMS

    Before every consignment for a solar energy project, register on REEIMS using your IEC: 2 days before arrival by air, 5 days by sea or land. One registration covers one port for 3 months[4].

  8. 8
    Mark the modules and ship

    Mark the Standard Mark with IS 14286 and IS/IEC 61730 references and the R-number[20]. Give your broker the CRS licence, the REEIMS certificate and the EPR certificates.

How does BIS registration work for solar panels?

The legal basis is MNRE's order, run by BIS. The Solar Systems, Devices and Components Goods Order, 2025 (S.O. 492(E), 27 January 2025) covers five products: crystalline modules, thin-film modules, storage batteries, PV inverters and grid-tied inverters[1]. Goods must meet the listed Indian Standards and carry the Standard Mark under a Scheme-II licence, the same scheme used for electronics CRS[26]. Goods made only for export are exempt[1].

Which standards. Crystalline modules must meet IS 14286 (Part 1):2023 and IS 14286 (Part 1/Sec 1):2023 (the Indian versions of IEC 61215-1 and 61215-1-1), plus IS/IEC 61730-1 and -2 for module safety[3]. Thin-film modules use Sec 2 (CdTe), Sec 3 (amorphous silicon) or Sec 4 (CIGS) instead of Sec 1[3]. See IS 14286 for the full history of the standard.

The efficiency condition. This is new in the 2025 order. BIS will not grant a licence unless the module reaches 18% (mono-crystalline and thin film) or 17% (poly-crystalline) at Standard Test Conditions[3].

Old licences. Licences granted under the 2017 order stay valid, but renewals and new registrations follow the 2025 order[3]. BIS allowed new applications on the old standards only up to 27 July 2025 and deletes non-compliant models from licences after the deadline[20].

The next change. IS/IEC 61730-1 and -2 have 2023 editions. Both sets can be used until 15 February 2027[2], and the CRS portal already lists both against PV modules[27].

Who applies. As for all CRS products, the licence is granted to the manufacturer for each factory, not to the importer[23]. A separate application is needed for each brand[12].

When did BIS registration become compulsory for solar panels?

The first order was MNRE's Solar Photovoltaics, Systems, Devices and Components Goods (Requirements for Compulsory Registration) Order, 2017, S.O. 2920(E) of 30 August 2017[28]. The CRS portal gives 31 March 2019 as the implementation date for both crystalline and thin-film modules[27].

Solar PV order notifications listed by BIS
DateNotificationWhat it didSource
30 Aug 2017S.O. 2920(E)First solar CRS order: IS 14286, IS 16077, IS/IEC 61730, IS 16221, IS 16169, IS 16270[28]
16 Apr 2018, 30 May 2018, 12 Oct 2018S.O. 1602(E), 2183(E), 5259(E)Amendments to the 2017 order (contents not opened by us)[29]
24 Jan 2023S.O. 444(E)Amendment; BIS's file is titled as a solar inverter extension[29]
27 Jan 2025S.O. 492(E)2025 order replaces the 2017 order; new standards and efficiency floor[1]
27 Jul 2025-2025 order in effect, per BIS[2]
5 Aug 2025S.O. 3597(E)Relief for inverters above 200 kW (not modules)[30]

What is ALMM and does it apply to imported solar panels?

ALMM is MNRE's Approved List of Models and Manufacturers. It comes from the ALMM Order of 2 January 2019, which set up List-I for modules and List-II for cells[5].

It is a buyer-side rule, not a customs rule. Only List-I modules may be used in Government projects, Government-assisted projects, projects under Government schemes, net-metering and open-access projects, and projects selling power to Government under section 63 of the Electricity Act[10]. The import policy condition DGFT added for modules is REEIMS registration, not ALMM[4]. ALMM is checked by the project side: the tender, scheme or net-metering approval your buyer works under.

ALMM depends on BIS. Enlistment stays valid only while the BIS registration is valid, and MNRE shows each unit's R-number on the list[13]. ALMM also has its own efficiency thresholds, higher than BIS's: 20.0% for utility-scale, 19.5% for rooftop and pumping and 19.0% for solar lighting (crystalline)[13].

Timeline of ALMM rules.

ALMM dates for solar modules, cells and wafers
DateWhat changedSource
2 Jan 2019ALMM Order issued (List-I modules, List-II cells)[5]
FY 2023-24Order held in abeyance; projects commissioned by 31 Mar 2024 exempt. A Feb 2024 re-imposition O.M. was itself put in abeyance[31]
31 Jul 2025First ALMM List-II (cells) issued; bid cut-off fixed at 31 Aug 2025[32]
1 Jun 2026List-II effective: List-I keeps only modules made with List-II cells; List-I(a) for exempt projects[5]
1 Jun 2028List-III (ingots and wafers) effective for all ALMM projects, including net-metering and open access[6]

Can imported modules be used in rooftop and government projects after June 2026?

From 1 June 2026, a module stays in ALMM List-I only if it uses cells from ALMM List-II, and makers that do not comply can be delisted[5]. Net-metering and open-access projects commissioned before 1 June 2026 were exempt from the cell rule[32]. A PIB release of 18 July 2026 reportedly extended that window for net-metering and open-access projects to those commissioned by 31 December 2026, while refusing a blanket extension for other projects[33]. The relief covers cells only; the modules must still be on List-I.

Separately, the CPSU Scheme Phase-II, Components B and C of PM-KUSUM and PM Surya Ghar: Muft Bijli Yojana have Domestic Content Requirement rules that mandate domestically made cells and modules[32]. Imported modules do not qualify for those schemes.

What this means for an importer. Imported modules can still be sold legally once BIS-registered. The open market for them is private captive, commercial and industrial buyers and exports that are not covered by ALMM. Check the buyer's project type before you order.

From 1 June 2028, List-I will include only modules made with ALMM-listed cells and wafers[6].

What is REEIMS registration for solar imports?

REEIMS is MNRE's Renewable Energy Equipment Import Monitoring System. DGFT Notification 40/2025-26 made it compulsory from 1 November 2025[4].

  • What it covers: goods under HS 70071900 (toughened glass), 85414200 (cells) and 85414300 (modules) used exclusively for solar energy projects[4].
  • When to file: at least 2 days before arrival for air cargo and 5 days for sea and land shipments[4].
  • Cost and validity: no fee; each registration lasts 3 months and is tied to one port, but can cover several consignments[4].
  • What you declare: the intended end use of the goods[4].

REEIMS is a monitoring step, not a quality approval. It does not replace BIS registration. Register in time; a shipment that arrives before its REEIMS registration is a policy-condition breach.

Do solar panels need e-waste EPR registration?

Yes. The E-Waste (Management) Rules, 2022 define e-waste to include solar PV modules, panels and cells, and Schedule I lists them under code CEEW14[7]. Anyone who imports EEE and offers it for sale is a producer[34], and no producer may do business without registering[34].

Solar is treated differently from other electronics. There is no recycling target for waste modules[34]. Instead, rule 12 requires you to[7]:

  • register on the CPCB portal;
  • store the solar waste you generate up to 2034-35 under CPCB's guidelines;
  • file annual returns up to 2034-35; and
  • keep a separate inventory of modules on the portal.

The portal is the E-Waste Management System at eprewaste.cpcb.gov.in[35]. Modules must also meet the RoHS limits, though the 2023 amendment added exemptions for cadmium and lead in solar PV[36].

Do solar panels need battery EPR, plastic EPR or LMPC registration?

Battery EPR: no, for a plain module. It applies only if you import batteries or equipment containing them[37]. A solar kit with a battery, or a solar storage battery, brings it in.

Plastic EPR: usually yes. An importer of any commodity in plastic packaging is an "importer" under the plastic EPR rules[15]. Stretch wrap, corner protectors and bags count. Register on CPCB's portal[15].

LMPC: depends on the buyer. Every importer of pre-packaged commodities for sale must register under rule 27[18]. But packages meant for industrial or institutional consumers are exempt from the retail-package provisions[17]. Pallets sold to EPC contractors are usually institutional; boxed panels sold to households through shops or online are retail.

What must be marked on an imported solar panel?

BIS Standard Mark. BIS's illustration for modules shows the IS 14286 (Part 1/Sec x) and IEC 61215-1-x reference, IS/IEC 61730-1, IS/IEC 61730-2 and the R-number[20]. The mark goes on the product, its package or both, legibly and indelibly[38], with text no smaller than Arial size 6[38] and www.bis.gov.in on the product or package[39]. See CRS labelling.

Nameplate data. The lab reports Pmax and module area so BIS can check the efficiency floor[20]. Keep the nameplate consistent with the test report.

Plastic EPR. Rule 11 asks for the registration number on plastic packaging, including importers' packaging[40]; a QR code is allowed[41].

Legal Metrology. Retail packs carry the importer's name and address, country of origin, net quantity, month and year of manufacture, MRP and consumer care details[17].

What should you check on a solar module label before it ships?

Check the nameplate, the carton and the pallet against this list at the factory. Our label checker and the product label checklist cover the general rules; CRS labelling covers the Standard Mark in detail.

How much does BIS and EPR approval cost for solar panels? A worked example

One crystalline module series, one brand, one factory, sold to private commercial buyers. Official fees only. The total is our arithmetic, not an official figure.

Official fees for one solar module series, first year (our arithmetic; excludes GST, lab, AIR and consultant charges)
ItemOfficial feeSource
BIS CRS application feeRs 1,000[11]
BIS processing fee (incl. one test report)Rs 50,000[11]
BIS annual licence fee (first year)Rs 1,000[11]
E-waste EPR registration, new producerRs 10,000[14]
E-waste portal annual maintenanceRs 5,000[14]
Plastic EPR registration (under 1,000 TPA)Rs 10,000[16]
REEIMS registrationNil[4]
Total, our arithmeticRs 77,000 plus GST on BIS fees-
Each extra test report (e.g. a second wattage family)+ Rs 20,000[11]
If you label for BEE (voluntary)+ Rs 0.025 per watt[8]

What does the solar panel cost example leave out?

  • Lab testing. IS 14286 and IS/IEC 61730 testing is long and sample-heavy; labs set their own prices.
  • The 2026 BIS fee change. A consultant reports the processing fee is now Rs 25,000 a year paid in advance[42]. BIS has not published a revised table we could open.
  • MSME concession. Micro and small Indian manufacturers had a Scheme-II fee concession, cut to 20% for all MSMEs from 1 June 2026[43]. It does not help foreign factories.
  • ALMM charges. We did not research MNRE's enlistment fees.

See CRS cost and EPR registration cost.

What does it cost to certify three solar module families?

About Rs 1,17,000 in official fees before GST and testing, if the three families need three test reports in one BIS application. This is our arithmetic. Module testing to IS 14286 and IS/IEC 61730 is the larger cost, and labs set their own prices; compare market quotes on BIS CRS registration costs or model your range in the compliance cost estimator and the BIS CRS fee calculator.

Official fees: 1 vs 3 module families, first year (our arithmetic; excludes GST, lab, AIR and consultant charges)
Item1 family3 familiesSource
BIS application feeRs 1,000Rs 1,000[11]
BIS processing fee (one test report included)Rs 50,000Rs 50,000[11]
Extra test reports at Rs 20,000 each-Rs 40,000[11]
BIS annual licence feeRs 1,000Rs 1,000[11]
E-waste EPR registration, new producerRs 10,000Rs 10,000[14]
E-waste portal annual maintenanceRs 5,000Rs 5,000[14]
Plastic EPR application, under 1,000 TPARs 10,000Rs 10,000[16]
REEIMS registrationNilNil[4]
Total, our arithmeticRs 77,000Rs 1,17,000-
Adding a family later by inclusion-Rs 30,000 incl. one report[11]

How long does it take to get solar modules approved and cleared?

Allow two to four months for BIS, mostly for testing, then plan REEIMS days before each shipment. The official clocks below are the ones you can hold an authority to; lab time is not regulated. For more on timing, see how long BIS registration takes.

Official time limits for solar module imports
StepOfficial clockSource
Send samples after the test requestWithin 60 days[25]
Apply for CRS after the test reportWithin 90 days[12]
BIS grant if everything is in orderAbout 20 working days[12]
REEIMS registration before arrival2 days (air) or 5 days (sea and land); valid 3 months, one port[4]
CPCB e-waste EPR shortcomingsFlagged within 25 working days; reply in 7[14]
CPCB plastic EPR15 days, else deemed[16]
LMPC importer registration (retail packs)Apply within 90 days of first import[18]
Move to IS/IEC 61730:2023Old and new run together to 15 Feb 2027[2]

Three common solar panel import situations

1. EPC contractor importing for a private factory rooftop. The modules need BIS registration[23] and REEIMS registration before arrival[4]. If the rooftop is under net metering, it needs ALMM List-I modules, and List-II cells too unless it is commissioned by 31 December 2026 under the reported relief[33]. Check whether your project uses net metering before you import.

2. Trader importing small panels for retail sale. You still need the factory's BIS registration in your brand[12], e-waste and plastic EPR registrations, and LMPC registration with full retail declarations[18]. Folding panels with a built-in battery add battery EPR[21].

3. Foreign module maker entering India. The factory applies for CRS through an Authorised Indian Representative who is an Indian resident[44]. To sell into government and subsidy-linked projects, it also needs ALMM enlistment, which is tied to its BIS registration[13]. Scheme projects with Domestic Content Requirements stay closed to imported modules[32].

Who is responsible for what: factory, importer, EPC or seller?

The factory holds BIS and ALMM, the importer holds REEIMS, EPR and LMPC, and the project developer answers for ALMM and domestic-content rules in its tender. Each party should ask for the others' certificates before money moves.

Who holds each solar module approval
PartyWhat it must hold or doSource
Foreign module factoryBIS CRS licence per factory and brand, through an Authorised Indian Representative[23][12]
Module maker seeking project salesALMM List-I enlistment, valid only while BIS is valid[13]
Importer (IEC holder)IEC, REEIMS for project shipments, e-waste and plastic EPR, LMPC for retail packs[45][4][7]
EPC contractor or developerUse ALMM modules where the project type requires it; meet DCR rules in scheme projects[10][32]
Distributor or online sellerDo not sell or store for sale modules without the Standard Mark[23]

Where do solar panel shipments get stuck?

Most holds come from paperwork that does not match the goods.

Common problems at clearance or sale for imported solar modules
ProblemWhy it mattersFix
No REEIMS registration, or registered for another portPolicy Condition 09 applies to 85414300 from 1 Nov 2025[4]Register 2 or 5 days ahead for the actual port[4]
Module model or wattage not on the CRS licenceUnregistered models cannot be imported or sold[23]Add the model by inclusion[46]
Licence still on IS 14286:2010Old-standard models are deleted from licences after the deadline[20]Retest to the 2023 series
Efficiency below the floorNo licence below 18% / 17%[3]Choose higher-efficiency models
Buyer needs ALMM, module not listedALMM projects can use only List-I modules[10]Confirm the buyer's project type before ordering
No plastic EPR proofCPCB asked Customs to verify it[24]Register as an importer

What happens if you import solar panels without these approvals?

BIS. The 2025 order says contraventions are punishable under the BIS Act, 2016, with BIS as the enforcing authority[3]. Under section 29(3) as enacted (later amendments not checked), the penalty is up to two years in prison, or a fine of at least Rs 2 lakh (Rs 5 lakh for repeat offences) extendable to ten times the value of the goods, or both[47]. BIS can also order a stop to supply and a recall[47].

E-waste. Environmental compensation can be levied on unregistered producers[34], and violations other than target shortfalls cost Rs 20,000, Rs 40,000 and Rs 80,000 for first, second and third defaults[48].

Legal Metrology. A retail package without the required declarations draws an improvement notice first, then a penalty of up to Rs 5 lakh, then a fine of Rs 25-50 lakh[49].

ALMM. There is no fine for selling a non-ALMM module to a private buyer. The risk is commercial: a non-ALMM module in a covered project can cost your buyer its subsidy or its net-metering approval.

What changes for solar panels in 2026 and 2027?

Five dated changes affect module importers. Follow updates on our 2026 rules ledger.

  • ALMM List-II (cells) from 1 June 2026 for List-I modules[5], with a reported net-metering and open-access window to 31 December 2026[33].
  • BIS licences run five years since the 25 February 2026 amendment[9].
  • IS/IEC 61730:2023 replaces the 2016 editions; both run together until 15 February 2027[2]. Plan partial retesting for existing models before then.
  • BEE 2026 regulations keep PV modules on the voluntary schedule[8].
  • ALMM List-III (ingots and wafers) from 1 June 2028 for all ALMM projects[6].

Where can you get help with solar module approvals?

Ask the factory first for its IEC 61215 and 61730 reports and any existing Indian R-number. Then:

Frequently asked questions

Is BIS certification mandatory for solar panels in India?

Yes. Crystalline and thin-film PV modules are covered by MNRE's Solar Systems, Devices and Components Goods Order, 2025, which requires a BIS Scheme-II licence and the Standard Mark[1]. The CRS portal shows modules as compulsory since 31 March 2019[27].

Which IS standard applies to solar panels now?

IS 14286 (Part 1):2023 and the technology section (Sec 1 for crystalline), plus IS/IEC 61730-1 and -2[3]. The older IS 14286:2010 is no longer accepted for new licences after 27 July 2025[20].

What is the minimum efficiency for BIS registration of solar modules?

18% at STC for mono-crystalline and thin-film modules and 17% for poly-crystalline modules[3]. ALMM enlistment has higher thresholds, such as 20.0% for utility-scale crystalline modules[13].

Do I need ALMM to import solar panels?

Not to import them. ALMM decides which modules can be used in government, government-assisted, scheme, net-metering and open-access projects[10]. If your buyer's project is one of these, the module must be on List-I.

When does ALMM List-II for solar cells apply?

From 1 June 2026. From then, List-I keeps only modules made with List-II cells[5]. Net-metering and open-access projects commissioned before that date were exempt[32].

What is REEIMS?

MNRE's import monitoring portal. Since 1 November 2025, modules, cells and solar glass for solar energy projects must be registered on it before import; it is free and each registration lasts 3 months[4].

What HS code do solar panels use?

85414300, photovoltaic cells assembled in modules or made up into panels; bare cells are 85414200[4].

Do solar panels have e-waste EPR targets?

No recycling targets. Producers must register, store solar waste up to 2034-35 and file annual returns instead[7][34].

Is a BEE star label needed for solar panels?

No. Solar PV modules are on BEE's voluntary list, with a label fee of Rs 0.025 per watt if you choose to label[8].

Can net-metering rooftop projects still use modules without ALMM List-II cells?

Only if commissioned by 31 December 2026, according to a PIB release of 18 July 2026 reported in the trade press[33]. The modules must still be on ALMM List-I[10].

Who applies for BIS for imported solar panels?

The manufacturer, for each factory; the licence is not granted to an importer[23]. A foreign factory acts through an Authorised Indian Representative resident in India[44].

How much do official fees come to for three module families?

About Rs 1,17,000 in the first year by our arithmetic: Rs 92,000 in BIS fees for three test reports in one application, plus Rs 25,000 for e-waste EPR registration, the e-waste portal charge and plastic EPR[11][14][16]. Testing and GST are extra.

Sources 49 documents, 47 official

Each number in the text links to the document below. Labels show the type of source; see our editorial policy.

  1. Gazette Solar Systems, Devices and Components Goods Order, 2025 (Gazette copy on BIS site) · 27 January 2025
  2. Official circular BIS guidelines for transition to IS/IEC 61730-1/-2:2023 (30 Dec 2025) · 30 December 2025
  3. Gazette Solar Systems, Devices and Components Goods Order, 2025 · 27 January 2025
  4. Gazette DGFT Notification 40/2025-26 (S.O. 4669(E)), copy hosted on MNRE's REEIMS portal · 10 October 2025
  5. Official circular MNRE O.M. No. 283/59/2024-GRID SOLAR, 9 Dec 2024 · 9 December 2024
  6. Official circular PIB release: Government Extends ALMM Framework to Solar Ingots and Wafers (18 Mar 2026) · 18 March 2026
  7. Gazette E-Waste (Management) Rules, 2022 · 2 November 2022
  8. Gazette BEE (Appliance Labeling and Compliance) Regulations, 2026 · 26 December 2025
  9. Official circular BIS notice: Revised Provisions for Licence Validity, Renewal and Annual Fee Payment under CRS (circular dated 27 May 2026) · 27 May 2026
  10. Official circular MNRE O.M. No. 283/64/2025-GRID SOLAR, FAQs on ALMM for solar PV cells (23 Sep 2025) · 23 September 2025
  11. Official portal BIS CRS Fee Structure (applicable w.e.f. 04 June 2018) · 4 June 2018
  12. Official circular Guidelines for Grant of Licence (GoL) under Scheme-II of Schedule-II, BIS (Conformity Assessment) Regulations 2018, Ref RG:01 · 20 August 2019
  13. Official circular MNRE O.M. 29 April 2024, Updation of ALMM List-I (Revision XXIV) · 29 April 2024
  14. Official circular CPCB SOP for grant of registration to Producers under E-Waste (Management) Rules, 2022 (April 2023; copy hosted by Pollution Control Board Assam) · 1 April 2023
  15. Gazette Plastic Waste Management (Amendment) Rules, 2024 - G.S.R. 201(E) (gazette copy hosted by TNPCB) · 14 March 2024
  16. Official portal CPCB SOP for Registration of Producer, Importer & Brand Owners through Plastic EPR Portal (15 Mar 2022) · 15 March 2022
  17. Official circular Lok Sabha Unstarred Question No. 2673 (07.08.2024): Legal Metrology (Packaged Commodities) Rules, 2011 - answer by MoS Consumer Affairs · 7 August 2024
  18. Official portal The Legal Metrology (Packaged Commodities) Rules, 2011 (G.S.R. 202(E), 7 March 2011) - copy hosted by Directorate of Legal Metrology, West Bengal · 7 March 2011
  19. Gazette G.S.R. 418(E), 29 May 2026 - Legal Metrology (Packaged Commodities) Third Amendment Rules, 2026 (Gazette of India, Extraordinary) · 29 May 2026
  20. Official circular BIS Guidelines for Implementation of Revised QCO for Solar PV Modules (27 Mar 2025) · 27 March 2025
  21. Official portal CPCB FAQs (General) under Battery Waste Management Rules, 2022
  22. Gazette Bureau of Energy Efficiency (Appliance Labeling and Compliance) Regulations, 2026 - Notification No. 5506/BEE/S&L/AL/2025-26 dated 26 Dec 2025, Gazette of India Extraordinary Part III Sec 4 (CG-DL-E-29122025-268894) · 26 December 2025
  23. Official portal About CRS - crsbis.in
  24. Court order CPCB compliance report to NGT in O.A. 993/2024 with O.A. 926/2024 (dated 06.07.2026) · 6 July 2026
  25. Official portal Registration - crsbis.in
  26. Official portal BIS - Products under Compulsory Certification, Scheme-II (Registration Scheme/CRS), last updated 26 Oct 2026 · 26 October 2026
  27. Official portal Products under CRS - crsbis.in (Products BIS list)
  28. Gazette Solar PV Goods (Requirements for Compulsory Registration) Order, 2017 · 30 August 2017
  29. Official portal BIS Scheme-II (Registration Scheme) product list
  30. Gazette MNRE S.O. 3597(E), 5 Aug 2025 · 5 August 2025
  31. Official circular MNRE compilation of ALMM orders and O.M.s (2020-2025) · 15 February 2024
  32. Official circular MNRE O.M. No. 283/64/2025-GRID SOLAR, FAQs (23 Sep 2025) · 23 September 2025
  33. Reported PIB (MNRE): No Change in ALMM Policy; Centre Provides Extended Relief Window for Select Solar Projects up to December 2026 · 18 July 2026Not yet confirmed officially
  34. Gazette E-Waste (Management) Rules, 2022 - G.S.R. 801(E), Gazette of India (CPCB copy) · 2 November 2022
  35. Official portal CPCB E-Waste Management System portal (home page)
  36. Gazette E-Waste (Management) Amendment Rules, 2023 - G.S.R. 61(E) · 30 January 2023
  37. Gazette Battery Waste Management (Amendment) Rules, 2023 - S.O. 4669(E) · 25 October 2023
  38. Gazette BIS Registration Dept circular 06.09.2019 on marking + Scheme-II para 6 and Annexures I-III (Gazette extract) + e-labelling circular 13.09.2017 · 4 June 2018
  39. Official circular BIS Registration Dept circular 06.09.2019 · 6 September 2019
  40. Gazette Plastic Waste Management (Second Amendment) Rules, 2022 - G.S.R. 522(E) · 6 July 2022
  41. Gazette Plastic Waste Management (Amendment) Rules, 2025 - G.S.R. 73(E), Gazette of India · 23 January 2025
  42. Reported IndiaLaw: BIS (Conformity Assessment) Amendment Regulations 2026 explained · 5 March 2026Not yet confirmed officially
  43. Gazette BIS (Conformity Assessment) Amendment Regulations, 2024, F.No. BS/11/11/2024 · 6 March 2024
  44. Official portal Nomination of AIR - BIS FMCS · 5 February 2026
  45. Official portal Foreign Trade Policy 2023, Chapter 2: General Provisions Regarding Imports and Exports (revised, v1.2.2)
  46. Official portal Inclusion and Renewal - crsbis.in
  47. Gazette The Bureau of Indian Standards Act, 2016 (Act No. 11 of 2016) · 21 March 2016
  48. Official circular CPCB Guidelines for Environment Compensation (EC) under E-Waste (Management) Rules, 2022 (August 2024; copy hosted by TNPCB)
  49. Gazette The Jan Vishwas (Amendment of Provisions) Act, 2026 (No. 8 of 2026), Gazette of India Extraordinary Part II Sec 1, 8 April 2026 (CG-DL-E-08042026-271642), copy hosted on dgma.gov.in · 8 April 2026

Where should you go next?

  • Product guides46 pages: every approval a product needs, product by product
  • Checklists7 pages: tick-box lists for each stage, from sampling to listing
  • Compliance costs7 pages: official fees and typical private charges, approval by approval
  • Free tools7 pages: approval checker, HS code finder, fee and cost calculators
Comploa Editorial DeskImport compliance researchers

We read the gazette notifications, regulator circulars and portal guidance behind Indian import approvals, and cite the document for every fact. When a rule changes, we update the page and its date. How we research and correct · About Comploa.

Related guides

Terms used on this page

Compulsory Registration Scheme (CRS)BIS's Scheme-II registration: manufacturers of notified products self-declare conformity to an Indian Standard, backed by a recognised lab report, and mark goods with a registration number.R-numberThe unique registration (licence) number BIS issues to a manufacturer under the Compulsory Registration Scheme, printed as part of the CRS Standard Mark on the product or package.Standard MarkThe mark BIS authorises a licence holder to apply to goods conforming to an Indian Standard, such as the ISI mark (Scheme-I) or the CRS registration mark (Scheme-II).Authorised Indian Representative (AIR)An Indian resident nominated by a foreign manufacturer to take responsibility, on its behalf, for compliance with the BIS Act, rules, regulations and licence conditions.EEE codeThe code (such as ITEW15 or CEEW1) that Schedule I of the E-Waste (Management) Rules, 2022 assigns to each type of electrical and electronic equipment covered by e-waste EPR.HS code (ITC(HS) code)The Harmonized System number used to classify traded goods; India's 8-digit version, the ITC(HS) code, is declared on the Bill of Entry for every import.BIS-recognised laboratoryA testing lab approved by the Bureau of Indian Standards under its Laboratory Recognition Scheme to test products against specific Indian Standards for BIS certification and registration.LMPC registrationRegistration of the name and address of a business that pre-packs or imports commodities for sale, under rule 27 of the Legal Metrology (Packaged Commodities) Rules, 2011.
Get alerts when solar panels rules change

New QCOs, deadline extensions and fee changes, sourced and dated. Only when something changes.

Free compliance check

Ship it once. Clear it first time.

Tell us the product, the model and where it is made. We reply with every approval it needs, the official fees, a realistic timeline and the order to file in.

  • Free, no obligation
  • Reply within one working day
  • Every fact sourced